Logistics Cold Chain
Project Description: 10.2-meter-high four-directional trolley intensive storage (-25°C cold storage), 16 four-directional trolleys, storage capacity of 5,326 trays, warehouse area of 3,500 square meters;
Supply Scope Of EQS: Four-directional trolleys, racking, conveyors, WMS, WCS, AGV system, cross-belt sorter;
Implementation Period: Total period of 145 days, design and manufacturing of 50 days, on-site installation of 40 days, single-machine debugging of 20 days, joint debugging of 25 days;
Project Benefits: Space utilization increased by 20%, 13 in-plant logistics personnel reduced, and 46 warehouse operation personnel reduced (picking operation personnel).